Summary of Daniel O’Donnell File, M346, National Archives

12/21/1861  Paid $19.15 for work done at unstated location. (Oct. 28) 37 ft gas pipe ($16.65), 1 two swing gas bracket ($2.50). Wm. E. Warren signs. (p. 111)

3/24/1862  Paid $71 for work done at unstated location. (Dec. 21) Putting up (111) one hundred and eleven stoves ($55.50), Capping eight stoves ($4), Putting up one stove & repairing ($1.50), Hauling stoves ($10). Capt. Wm. E. Warren signs. (p. 56)

4/30/1862  Paid $58.50 for work done at General Hospital #1. (Dec. 12) 14 feet 1 ¼ lead pipe ($10.50), 18 feet water pipe ($13.50), 12 feet culvert pipe ($12), 1 iron enameled sink ($8), 1 compression cock ($5), 1 stop cock ($3), 1 lead stench trap ($4), connection pipes ($2.50). “The Q. M. Dept will pay this acct on the approval of the Surg. Genl to be charged to Med Dept. [illegible] N. W. E.” Surgeon General Moore approves, Surg. C. B. Gibson signs. (p. 80)

6/30/1862  Paid $67 for work done at St. Charles Hospital [General Hospital #8]. (June 14) 15 feet water pipe ($15), 2 feet 6 in waste pipe ($2.50), 2 water cocks ($10), 12 lbs solder ($12), cleaning & repairing closets ($15), putting up 2 sinks ($2.50), time plumbers & help ($10). Surgeon General Moore approves, Surg. J. C. Herndon, in charge St. Charles Hospital, signs. (p. 94)

7/11/1862  Paid $205.50 for work done at Crew’s Factory, Greanor’s, Franklin St. Hospital, Tolbert’s Factory on 18th street, Palmer Factory, Garrett’s Factory & 22nd & Cary Sts. (Crew’s Factory, May 23)5 lbs sheet lead ($3.75), 1 paper tacks & ½ day work for plumber ($2.75). (Greanor’s, June 26) time of plumber setting trough ($5). (Franklin St. Hospital, June 26) repairing hydrant with new screw ($7.50). (Tolbert’s Factory, 18th Street, June 30) 1 ball cock ($4) 2 ft lead pipe ($2), repairing water closets ($5), repairing urinal, time &c ($10.50). (Palmer’s Factory, July 2) 24 feet water pipe ($24), 5 joints ($5), 1 stop cock ($5), 6 lbs sheet lead ($4.50). working up culvert time &c ($20), repairing water cock ($2.50). (Garrett’s Factory, July 2) work at closets time &c ($40). (22d & Cary Sts, July 5) time of plumbers ($30), 20 feet waste pipe ($25), 1 stop cock ($5), 4 lbs solder ($4). T. P. Turner signs. (p. 128)

7/14/1862  Paid $127.75 for work done at General Hospital # 9. (July 11) 71 ft Gal 1 ¼ pipe ($88.75), 1 shop cock & iron bore ($9), 1 iron hydrant ($30). Surgeon General Moore approves, Surg. Wm. H. Coffin signs. (p. 76)

7/19/1862  Paid $120 for work done at General Hospital #4. (June 18) 1 copper pan to water closet ($7.50), 10 lb putty ($2.50), 3 ball levers ($3), 4 plumbers joints ($4), repairing range & new grate ($10), cleaning & over hauling closets ($30). (June 22) repairing gas pipe ($1). (July 8) cleaning & repairing culvert & closets ($28), 4 feet lead pipe ($4), July 11) cleaning culvert ($25), 2 feet 6 in stove pipe ($5). Surg. Jno. B. Read signs. (p. 22)

7/19/1862 Paid $287 for work done at General Hospital #7. (June 26) 68 feet lead pipe ($68), 26 plumbers joints ($26), 3 5/8 Bibb cocks ($18), 1 Ball cock ($4), 12 pair lead tacks & screws ($12), 2 funnel pipes to closets ($7), 2 Ball levers ($4), time & solder on old work ($20). (June 30) work on culvert ($5), 10 feet 5 in iron pipe ($25), 1 iron bend ($5), 8 feet water pipe ($8), 1 stop cock ($5), cleaning closet sheet lead &c ($5). (July 9) cleaning waste pipes to sinks ($2.50). (July 13) cleaning culvery on Sunday ($10). (July 17) 15 feet 5 in iron pipe ($37.50), 1 iron bend ($5), time of plumber & bricklayer ($20). Surg. Wm. J. Moore signs. (p. 30)

8/14/1862  Paid $370.45 for work done at Union Hospital. (June 30) Refitting 78 feet gas pipe ($31.20), 8 1 swing gas brackets ($24), 6 2 swing gas brackets ($30), 6 2 light pendants ($42), 4 1 light pendants ($24), 18 feet gas pipe ($13.50), cutting & repairing 3 chandl ($5), cutting & repairing 3 pendants ($2.50), 12 new gas burners ($6). (July 8) 33 feet waste pipe ($41.25), 18 feet water pipe ($18), 2 Bibb cocks ($12), 1 shower cock & shower ($12), 1 stand & waste to bath ($6), 21 plumbers joints ($21), time on old work ($25), painting bath tub ($3). (July 14) 12 feet water pipe ($12), 1 stop cock ($6), 1 Bibb cock ($6), 2 feet 1 ½ in waste pipe ($3). (July 22) cleaning out waste pipe ($1). (July 25) 4 feet 1 ½ in waste pipe ($6), 4 feet 1 ¼ in waste pipe ($5), 9 plumbers joints ($9), 1 foot water pipe ($1), time of Bricklayer paving ($5). Surg. F. Sorrell, inspector of hospitals, approves, William A. Carrington, Surgeon in charge, signs. (p. 24)

8/16/1862  Paid $192.87 for various plumbing, carpentry and paving work at Government Bakery. (July 27) 15 feet lead pipe ($15), 5 feet 6 in 1 in lead pipe ($6.87), 3 feet 1in iron pipe ($3), 2 feet ¾ galvanized pipe ($1.50), 1 1in T ($2), 1 ¾ T ($1), 1 ¾ stop cock ($6), 1 5/8 stop cock ($5), 1 ball & cock ($8), 5 plumbers joints ($5), 5 lead tacks &screws ($2.50), time plumbers ($10), paving engine room ($2). (Aug. 12) 1 O’Donnell pump ($125). Peter Tinsley, agent, signs. (p. 6)

8/18/1862  Paid $53.75 for work done at General Hospital #5. (July 16) 38 feet water pipe ($38), 1 5/8 finished stop cock ($6), 1 hose screw ($2.50), 5 plumbers joints ($5), 2 fair lead tacks ($2), 2 plumbers hooks ($.25). Surgeon General Moore approves, Surg. R. W. Lunday signs. (p. 126)

8/28/1862  Paid $280.75 for work done at 22nd St, Libby Prison, and Palmer’s Factory. (22nd Street. July 11) cleaning culvert ($20) cleaning culvert – Libby ($20). (Libby Prison July 16) 7 feet 1 ½ galv iron pipe ($10.50), 2lbs solder ($2.50), 1 brass plug & washer to bath ($3.50). (Palmer’s Factory July 19) time on culvert ($35). (July 23) 1 foot pipe & 2 joints ($3). [Remainder of bill is for work done at Libby Prison] (July 29) 1 foot waste pipe & 2 joints Cleaning pipe ($4.25). (Aug. 1) cleaning culvert & repairing water pipes ($10.75), 1 plug & washer to bath ($4.50), time & soldier for 2 plumbers ($10). (Aug. 1 & 8) setting stench trap ($5). (Aug. 8) 3 pr lead tacks ($1.50), 2 – 5/8 stop cocks ($12), 5 plumbers joints ($5), 4 ft 1 ½ lead pipe ($6) 2 ??? tacks ($1), cleaning culvert ($15). (Aug. 9 & 13) time of plumber & help ($35), time of plumber & lad on culvert ($35). (Aug. 13 & 19) over hauling water pipe ($2.50), repairing water pipe & cleaning culvert ($12.75). (Aug. 22) repairing water pipe time & solder ($4) stone paving ($22). T. P. Turner signs. (p. 114)

9/17/1862  Paid $41 for work done at Banner Hospital [General Hospital #12]. (June 18) cleaning culvert & repairing water closets ($35), carpenters work ($6). Surg. Wm. Alex Thom signs. (p. 74)

9/17/1862  Paid $314.50 for work done at The Confederate States Prison [Castle Thunder]. (Aug. 15) Refitting 157 feet gas pipe ($78.50), 29 feet new gas pipe ($29), 14 plugs ($14), cutting & hanging 12 fixtures ($12), 1 2-light pendant ($4). (Aug. 19) refitting 20 feet gas pipe ($10), hanging gas fixture ($1) 1 T. & hanging 2 brackets ($2), 20 feet water pipe ($25), 1 stop cock ($6), 3 lbs solder & 1 pair tacks ($5). (Aug. 20) refitting 20 feet gas pipe ($10), paving yard Ricks bill ($42). (Sept. 5) working up brick walls ($5). (Sept. 9) 28 feet gas pipe ($42), 1 1-light pendant ($4). (July 24) cleaning culvert time &c ($25). “A portion of this work was done before I took charge of the building but as I knew of the work I sign it. Jno. H. Winder, B Gen.” G. W. Alexander signs. (p. 106)

9/30/1862  Paid $219.75 for work “done at the C. S. Mil Prisons on 18th St & 20 & Cary Sts.” (Aug. 9) cleaning privies & walling up door ($22). (Sept. 5) putting up stove at Libby Prison ($8). (Sept. 15) 31 ft water pipe ($46.50), 2 cocks ($12), 21 lbs sheet lead ($15.75) & 3 lbs solder ($6), time of laborer ($7.50), 1 water closet ($75). (Sept. 25) 18 ft water pipe ($27). Winder approves, Capt. Th. P. Turner signs. (p. 58)

10/30/1862  Paid $30.50 for work done at Eastern District Prison [Castle Thunder]. (Sept. 26) 1 gas bracket & repairing pipe ($7.50). (Oct. 20) refitting gas pipe & 1 bracket ($14), piecing metre pipe ($6). (Oct. 25) 3 gas burners ($3). Winder approves, G. W. Alexander signs. (p. 28)

11/1/1862 Paid $92 for work done at “the Western District Prison.” (Aug. 30) 32 feet gas pipe ($32), 3 2-light gas pendants ($18). (Sept. 5) 6 lb sheet lead ($3), cleaning pipe ($3), 2 strainers ($2), setting bath & solder ($7). (Sept. 26) altering gas pipe & 2 burners ($8). (Oct. 4) Setting bath & lead pipe ($15), cutting & fitting furnace pipe ($4). Capt. Th. P. Turner signs. (p. 60)

11/13/1862  Paid $154.50 for work done at General Hospital #7. (July 24) fitting 120 feet gas pipe ($120), 25 feet gas pipe ($25), hanging 4 brackets ($4), repairing fixtures ($1.50). (July 31) repairing water cock ($2.50). (Sept. 13) repairing water cock ($1.50). Surg. Wm. J. Moore & Wm. E. Warren sign. (p. 124)

11/30/1862  Paid $505.50 for work done at “the Barracks Cor 21st & Cary Sts.” (Sept. 5) Repairing water pipe ($2.50), repairing gas pipe & furnishing 3 ft pipe ($5.50). (Oct. 14) repairing gas pipe ($2.50) repairing 20 gas fixtures ($8.50). (Nov. 4) 18 lb stove pipe ($27), 5 65 lb stove pipes ($97.50). (Nov. 5) Putting up 9 stoves & repairing pipe ($225), 1 stove ($30), cleaning 14 privies ($53). (Nov. 14) 1 stove for Commandant’s office ($26), 13 lb stove pipe ($19.50), repairing 20 gas fixtures ($8.50). Capt. Jno S. Leach signs. (p. 10)

11/30/1862  Paid $565.75 for work done at C. S. Military Prison [Libby Prison]. [Oct. 14] Refitting 100 ft Gas Pipe ($50), 2 pendants ($16), Repairing Water Cock ($1.50), Working up Wall ($4.75) [Oct. 17] 26 ft Gas Pipe ($26), 1 Urine Basin ($12), 6 ft Lead Pipe ($9), 2 lb solder & lime (10.50). [Oct. 25] 26 lb Stove Pipe ($39), Repairing Water Pipe ($3), 2 tin funnels for Hospital ($3). [Nov. 1] 2 Stoves ($60), 48 lb Stove Pipe ($72), Repairing & putting up 7 stoves ($75), repairing water cocks ($6), 1 Gas Drop Light ($5). [Nov. 4] 1 Large Stove ($50), 82 lb Stove Pipe ($123) Capt. Th. P. Turner signs. (p. 8)

12/4/1862  Paid $110 for work at General Hospital #2. (Dec. 2) 15 feet of Gas Pipe ($30), one 2 light pendant ($12), refitting 22 feet old pipe ($11), repairing stove pipe & 2 stoves ($25), repairing tin ware ($5), 5 feet of waste pipe ($10), 2 lbs of zinc ($2), lime & solder ($15). Surgeon James M. Holloway signs. (p. 18)

12/15/1862  Paid $5 for “repairing water closet at Western District Prison.” R. M. Booker signs. (p. 44)

12/16/1862  Paid $5,328 for work done at General Hospital #1. “Putting up steam boilers, bath tubs and the necessary piping cocks &c as per contract with Surg. C. B. Gibson at Hospital No. 1.” Wm. E. Warren signs. (p. 34)

12/31/1862  Paid $10 for 2 gas burners for Gen. Winder’s office on April 3. Winder approves and signs. (p. 20)

12/31/1862  Paid $504.75 for work at “the Barracks Cor 21st & Cary Sts.” (Nov. 15) 5 plumbers joints ($10), 8 feet lead pipe ($16), 1 iron strainer ($2.50), Lead Tacks ($1), repairing cocks ($3.25), 5 ft 4 in tin pipe ($15). (Nov. 16) 9 ft 1 ½ inch tin pipe ($13), 3 elbows ($9), 4” lead pipe ($8) 2 lb solder ($4). (Nov. 17) 2 stoves ($100), cutting holes in hall ($5). (Nov. 25) 2 stoves ($100), 30 lb stove pipe ($45). (Nov. 28) Moving & putting up stoves ($20). (Dec. 1) 10 lb stove pipe ($15), cleaning 3 privies ($50). (Dec. 7) 13 ft 1 ½ in Lead Pipe & 6 hooks ($22.50). (Dec. 27) Putting up stoves & pipe ($15), repairing gas ($5). Capt. Jno. S. Leach signs. (p. 14)

12/31/1862 Paid $565 for work done at C. S. Military Prison [Libby Prison]. (Dec. 10) 150 feet 1 ½ in iron pipe ($375), 1 water cock for urinal ($6), 22 lb sheet lead ($22). (Dec. 25) Putting down culvert in street ($45), removing pipe ($40), 6 feet water pipe ($9), 13 lb solder ($26), 24 hooks ($6), 1 stop cock ($12), 1 water cock ($12), 8 pair tacks & screws ($12). Winder approves, Capt. Th. P. Turner signs. (p. 26)

12/31/1862 Paid $60.75 for work done at unstated location. E. Griswold signs. (p. 36)

12/31/1862 Paid $121.50 for work done at “the church cor 9th & Cary Sts formerly used as a guard house.” (Dec. 24) 35 lbs stove pipe & stove ($92), 16 lbs stove pipe ($24), putting up stove & pipe ($5.50). Capt. T. P. Turner signs. (p. 62)

1/10/1863 Paid $463 for work done at C. S. Military Prison [Libby Prison]. (Jan. 10) 129 feet lead pipe ($258), 7 cocks & 2 doz hooks ($94), 18 pairs tack & screws ($27), 12 lb solder ($24), taking down privies ($35), cleaning out culverts ($25). Capt. Th. P. Turner signs. (p. 46)

1/13/1863  Paid $40 for “repairing stone pavement at C. S. Military Prison [Libby Prison].” Capt. Th. P. Turner signs. (p. 42)

1/13/1863  Paid $26 “For repairing Water Pipe in Bakery” at Camp Lee. Capt. D. G. Meade signs. (p. 3)

1/14/1863  Special requisition from General Hospital #17 “to repair waste pipe of one of the water sinks.” “The pipe leaks badly and keeps the floor constantly wet.” Surg. J. B. Ficklin signs. (p. 68)

1/16/1863 Paid $381.50 for work done at General Hospital #2. (Dec. 12) 1 iron sink ($18), 1 water cock ($12), 2 feet water pipe ($4), 9 feet waste pipe ($22.50), 10 lbs zinc ($15), putting up stoves ($14), days work of 2 plumbers on Sunday ($20). (Dec. 16) 1 large range ($225), 1 tin kettle ($10), 26 lb sheet iron ($39(, 2 gas burners ($2). Surg. James M. Holloway approves, Capt. Wm. E. Warren signs. (p. 72)

1/16/1863  Paid $50.50 for work done at General Hospital #2. (Jan. 3) 2 ft 6 in of 2 in lead pipe ($10.50). (Jan. 10) 2 sheet iron pans ($30), putting up stove ($5), 2 lbs solder & repaint cock ($5). Surg. James M. Holloway approves, Wm. E. Warren signs. (p. 122)

1/20/1863  Paid $60.50 for work done at Eastern District Prison [Castle Thunder]. (Jan. 10) 2 5/8 stop cocks ($24), 1 Bibb Cock ($12), 2 ft water pipe ($4), 6” solders ($12), 1 1 ¼ lead pipe ($2.50), 1 copper rose & solder ($6). Winder approves, G. W. Alexander signs. (p. 40)

3/4/1863  Paid $148 for work done at General Hospital #17. (Jan. 16) repairing water pipes ($10), cleaning culvert ($125), 5 feet 4 in tin pipe ($10), 2 feet 1 ½ in tin pipe ($3). “The surgeon in charge certifies that the services were rendered. The charges in his opinion are exorbitant.” Surgeon J. B. Ficklin signs. (p. 66)

4/9/1863  Paid $95 for work at “Barracks.” (Jan 21) clearing culvert ($30). (Jan. 29) 9 feet gas pipe ($18), 1 gas bracket ($5). (Feb. 6) 1 wood sink ($12), 12 feet 1 ¼ waste-pipe ($30). Capt. Jno. S. Leach signs. (p. 12)

4/9/1863  Paid $410.25 for work done at Libby Prison & Hospital. (Jan. 10) repairs on ballcock ($2), brick work on fire places ($6). (Jan. 16) 34 lbs sheet iron pipe ($68), putting up 3 stoves ($25), 2 lbs lime ($4), 2 iron rods & 1 iron curtain[?] for [?] ($4). (Jan. 27) 3 gas burners & repairing gas pipes ($11). (Feb. 7) repairing water pipes ($3), repairing wash bin ($6.50). (Feb. 16) 25 lbs sheet lead & tacks ($37.50) Iron ??? ($2), 3 5/8 inch strip & waste cock ($48) 29 ft pipe ($65.25), 17 feet water pipe ($42.50), brick work ($20), lime & solder – hook & screws ($65). Jackson Warner signs. (p. 86)

4/9/1863  Paid $95 for work done at Mayo’s Factory. (Jan. 26) cleaning culvert ($45), putting up stoves & repairing pipe ($50). Jackson Warner signs. (p. 90)

4/9/1863  Paid $113 for work done at Castle Thunder. (Jan. 27) repairing gas fixtures ($8), 6 gas burners ($12) & 1 urine box ($25), 3 feet water pipe ($6), time of ??? ($6), 22 lbs stove pipe ($44), repairing gas bracket ($2), cleaning pipe ($7). (Jan. 29) cutting & repairing gas pipe ($5). “This bill to me looks high but stove pipe is ‘worth its weight in silver.’ This is full up to date.” G. W. Alexander signs. (p. 108)

4/18/1863  Paid $120 for work done at General Hospital #1. (Jan. 8) repairing oven with sheet iron ($40). (Jan. 10) putting up stove ($5). (Jan. 13) 11 lbs stove pipe ($22), time of tinner’s help ($10). (Jan. 16) repairing wash kettle ($15). (Jan. 28) cleaning waste pipe & repairing cocks ($8). (Feb. 19) time plumber’s help ($5). (Mar. 7) repairing furnace pipe ($5). (Mar. 14) 1 foot 6 in lead pipe & solder ($7), 1 copper strainer ($3). Carrington approves, Surg. C. B. Gibson signs. (p. 48)

6/8/1863  Paid $15 for work done “at Palmer’s Factory opposite Castle Thunder.” (May 11) repairing water ??? ($3), cleaning waste pipe ($12). Jackson Warner signs. (p. 88)

6/8/1863  Paid $109 for work done “at the Barracks corner Cary & 21st Streets.” (May 11) taking down gas fixtures & repairing water pipe ($14), (May 20) 5 gas brackets ($60), hanging & repairing fixtures ($14), capping up pipes ($21). Jackson Warner signs. (p. 118)

6/8/1863  Paid $407 for work done at C. S. Military Prison [Libby Prison]. (Feb. 29) repairing water pipe ($5). (Apr. 10) repairing water pipe ($5). (Apr. 17) cleaning service pipe ($5), (Apr. 28) 1 water cock & lead pipe ($20). (May 4) 2 feet lead pipe & solder ($10). (May 19) taking down & refitting 115 ft old gas pipe ($143), furnishing 44 ft gas pipe ($110), 3 two light pendants ($52), 1 harp pendant ($15), 1 three-swing gas bracket ($16), 7 gas fittings ($14), hanging & repairing 4 pendants ($12). Jackson Warner signs (p. 120)

7/16/1863  Paid $35 for work done on the C. S. Steamer Beaufort. (May 14) 1 cooking stove & fixtures ($30), repairing copper and tin ware ($5). Jno H. Parker signs. (p. 116)

7/22/1863  Paid $80 for work done at General Hospital #2. (Feb. 2) 2 feet 6 in lead pipe ($6), 2 plumbers joints ($4), cleaning waste pipe ($1.50), repairing gas fixtures & tin ware ($11.50). (March 19) 2 feet 1 ½ lead pipe ($5), cleaning waste pipe time &c ($15), 21 ¼ sockets ($4), 1 copper strainer ($3). (April 1) repairing gas ($10), tin ware ($5). (May 25) repairing tin ware ($15). Wm. A. Carrington approves, Surg. James M. Holloway signs. (p. 32)

7/22/1863  Paid $20 for work done at General Hospital #2. (June 16) repairing gas ($15), rooter cock ($5). Wm. A. Carrington approves, Surg. James M. Holloway signs. (p. 64)

10/19/1863  Paid $50 for work done at Barracks, 25th & Main Sts. (Oct. 19) repairing water pipes & gas ($20), repairing water pipe to privy ($30). Winder and J. W. Coker [Co. C, 32 NC] commanding post, approve, Capt. Geo. McH. Gish, Commanding Barracks, 25th & Main Sts., signs. (p. 84)

10/19/1863  Paid $44 for work done at unstated location, but probably Barracks, 25th and Main Sts. (Oct. 19) 7 gas fittings ($14), 2 gas brackets ($30). Winder approves, Capt. J. W. Coker [Co. C, 32 NC] commanding post signs. (p. 96)

10/22/1863  Paid $190 for work done at unstated location, but probably Barracks, 25th and Main Sts. (Oct. 19) refitting 60 feet gas pipe ($120), refitting & running 35 feet water pipe ($70). Winder approves, Capt. J. W. Coker [Co. C, 32 NC] commanding post signs. (p. 82)

10/23/1863  Paid $50.50 for work done at the Provost Marshal’s, 9th & Broad St. (Feb. 19) 7 feet gas pipe ($17.50), repairing gas fixtures ($3). (Mar. 23) cleaning 2 closets ($15), repairing water cocks ($5), carpenter work ($5). (July 15) cleaning closet ($5). Winder approves, Maj. E. Griswold signs. (p. 78)

11/26/1863  Paid $5 “for repairing gas fixtures” at unstated location on Nov. 14. Maj. William Norris, Chief of Signal Corps, signs. (p. 50)

5/3/1864  Paid $50 for work done at the Provost Marshal’s office (Maj. Carrington’s). (Feb. 25) 1 sheet iron elbow for stove ($15), cleaning gas pipes ($30), repairing stove pipe ($5). Winder approves, I. H. Carrington signs. (p. 100)

5/7/1864  Paid $1,341 for work done at Libby Prison. (Mar. 31) 8 lb iron & 7 ft lead pipe ($129), 1 lead bind & pair tack ($47), 1 lot solder ($122), 1 copper strainer & water pipe 12 ft ($71), 10 lbs sheet lead & solder ($130), 1 stove & 7 lbs sheet iron ($249), 5 lbs stove pipes & 1 bell completed ($85), 7 plumber joints ($70), 15 lbs sheet lead & 2 copper strainers ($55), 14 lead flanges & 15 lbs red lead ($95), 4 pair lead tacks & scrims ($20), 6 ft water pipe & 3 lead flanges ($33), 7 pair lead tacks & 14 plumbers joints ($175), 3 copper strainers & 25 lbs sheet lead ($60). Winder approves and Jackson Warner signs. (p. 52).

5/3/1864  Paid $25 “for work done in Brig Genl Winder’s office.” (Feb. 17) 1 stop cock & repairing gas ($25). Winder approves, John A Parkhill signs. (p. 98)

5/7/1864  Paid $470 for work done at Libby Prison. (Mar. 31) 16 ft water pipe & 6 ft 3 in tin pipe ($120), 3 lead flanges & 3 joints ($36), 16 ft water pipe ($104), 7 in waste pipe ($49), 2 lead flanges & 2 strainers ($16), 3 pair lead tacks & 9 joints ($105), 6 hooks ($5), 1 gas bracket ($35). Winder approves, Jackson Warner signs. (p. 54)

5/7/1864  Paid $112 for work done at “Palmers Factory & Castle Thunder.” (Mar. 31) 5 feet of new gas pipe ($30), gas bracket & 6 feet 1 ¼ in wash tin. ($82). Winder approves, Jackson Warner signs. (p. 104)

8/30/1864  Paid $20 for work done at Castle Thunder. (June 18) repairing water & gas pipes at Castle Thunder. L. W. Richardson approves, C. Morfit signs. (p. 38)

11/8/1864  Paid $250 for work done at Winder Hospital. “repairing two force & lift pumps with new valves bolts screws & solder furnished to Winder Hospital.” John Grubbs, post adjutant, and Carrington approve, Surgeon A. G. Lane signs. (p. 102)

11/15/1864  Paid $158 for work done at Castle Thunder. (April 8) Repairing lamp & gas fixtures ($30). (April 22) 1 hydrant screw fitted in ($40). (April 25) 1 stop cock & 2 joints ($60), 1 foot lead pipe & 1 pair of tacks ($18), cleaning waste pipe ($10). “This work was done at the time there was no Quarter Master for this prison and was a military necessity therefore the bill should be paid. L. H. Richardson, Capt & A P M comdg” Gen. Gardner approves, Jackson Warner signs. (p. 92)

11/15/1864  Paid $282 for work done at unstated location on June 28, 1864. Surg. Wm. A. Carrington, Medical Director, approves, Capt. Jackson Warner signs. (p. 16)

No date      Special requisition from General Hospital #17, 21st street between Main & Cary “to clean out the sewer of the privy – the sewer having become obstructed.” Surg. J. B. Ficklin signs. (p. 70)

Go to top